Build timeline planner

Choose your project type to see a staged programme with indicative week ranges. Planning-heavy routes take longer — read our extension timeline guide for what happens each stage, or use the PD Quick Check to sense-check your approval route.

Typical programme: week 16 – week 33 from design start to handover (approvals and site conditions vary).
  1. 1. Design & surveyWeeks 14 (24 wks)
  2. 2. PD checks & LDC (if needed)Weeks 38 (26 wks)
  3. 3. Party wall & enablementWeeks 57 (13 wks)
  4. 4. Structure & weather-tight shellWeeks 613 (48 wks)
  5. 5. First fix (M&E, insulation)Weeks 1013 (24 wks)
  6. 6. Second fix (plaster, joinery)Weeks 1214 (23 wks)
  7. 7. Finishes & snaggingWeeks 1417 (24 wks)
  8. 8. Handover & certificationWeeks 1616 (11 wks)

Disclaimer: Programmes are indicative. Planning decisions, party wall awards, weather, and specification changes can extend timelines. Use this as a planning guide, not a contract programme.